FTA: WHO or WHAT One Knows?

In 2011 the Federal Trade Administration (FTA) released a RFP to perform a study: Positive Train Control for Commuter and Regional Rail Systems. The stated objective of the RFP was to “evaluate the safety and reliability of PTC technology in commuter rail and regional rail operating environment, and to recommend the best practices in the implementation of PTC systems”. Without question, this proposed study had great potential benefit for commuter and regional rail operators. As such, the final report of the study was to be provided by June 30, 2013. After several years of seeing nothing from FTA, I confronted a FTA official as to the status of the report. I received no meaningful response (basically I was brushed off) , and I let ago of following this study as a fatuous effort by FTC that hopefully didn’t result in anyone being paid the $900k budgeted for the study.

Forward to July 2017 when the Final Report was released 4 years late: Technical and Safety Evaluation of the Southern California Regional Rail Authority PTC Deployment Project. Unfortunately, the study and the resulting Final Report was a total sham as demonstrated by the contents of the report as explained below.

To understand my issues with the study, I need to state first that I headed a team of well-experienced railroad consultants that responded to the RFP, and we were not selected. Not being selected is not the issue here IF indeed had a credible consultancy been selected. However, that is clearly NOT the case as I explain below. To be blunt, it appears to me that the selection of the University of Southern California (USC) team of professors was done by whom they knew, and NOT by what they knew. The proof of my position is readily noticeable in the report submitted by USC. I address 3 areas to make this point: PURPOSE, TIMING, & CREDENTIALS.

PURPOSE: It was clear to my team that the primary purpose of the study was to explore the issues of implementing PTC from a commuter and regional rail perspective, AND to present that information in a timely fashion that would be valuable to those operations. We knew that a primary issue would be the operating rules of these agencies were not being considered by the freight railroads via the Interoperability Train Control (ITC) committee. In fact, that has indeed been proven to be the case. In short, this means that the PTC handling of operating rules being deployed by freight railroads is not truly aligned with the requirements of the commuter railroads specifically. For example, consider the recent accidents within passenger terminals were the train accelerated resulting in fatalities. PTC if properly designed for commuters could readily have prevented this situation, but that was not done so by the freight railroad’s Interoperable Train Control (ITC) committee given its freight-only perspective. USC did not have the credentials, yet alone the insight to recognise this critical point.

Simply stated as to PURPOSE, the report is critically constrained for commuters in that it didn’t address critical PTC issues that are specifically oriented to such operations.

TIMING: The July 2017 report provided by USC was 4 years late, and hence is at best a “reactive” analysis versus a “proactive” analysis that could have been valuable to passenger operations. In short, this report is meaningless as to providing assistance to other agencies: the horse was already out of the barn, if you will.

Simply stated as to TIMING, the report was totally useless as to assisting the other passenger operations with their activities.

CREDENTIALS:
One has to read no further than the study’s ASTRACT to realize the lack of credentials of the USC team of professors without any notable railroad domain expertise. I quote: “Positive Train Control (PTC), often referred to as Communication Based Train Control (CBTC) …”. This statement is totally wrong and naïve as well; I don’t know how this major point got past the USC team of authors, as well as FTA. That is,

• PTC is a NON-VITAL, overlay enforcement system to prevent train accidents due to human errors.
• CBTC is a VITAL traffic control, management, and enforcement system

For my purposes here, VITAL is best defined as the means by which movement authorities are generated, i.e., the integrity of train movements, whether that be wayside equipment, office software, or an individual. PTC does not generate movement authorities and hence is not vital.

Simply stated as to CREDENTIALS, USC clearly did not understand PTC as well as lacking the ability to work with the PTC community as they stated in their report; they were shunned. They are outsiders without credible domain knowledge, thereby resulting in a useless analysis that provided no real value.

In conclusion, FTA awarded a project to USC that was not warranted at best, and that suggests irresponsible, if not unethical, practices by FTA as to the use of U.S. funds.

Given that there appears to be no current FTA Administrator, I submitted yesterday my letter of complaint (noting the above points) to the Associate Administers of Administration, Program Management, and Research, Demonstration and Innovation. I requested the courtesy of a response from these individual to explain how this study was awarded, apparently not monitored as to delivery (again, 4 years late), and yet accepted starting with the amazingly naïve, false equivalency of PTC to CBTC. So! Will one or more of them respond to my letter, and then proceed to have the report corrected? Or, will it be brushed under the rug and ignored since it is valueless?

Teddy Bears Revisited: Practical Technology Solutions

It is time for me to revisit my Teddy Bears” (TBs) postings on this blog in 2010. TBs are those perspectives / beliefs stated by railroaders, suppliers, and regulators to rationalize they are doing the right thing in their respective roles. However, when viewed objectively by individuals without any financial or organizational conflict, e.g., independent consultants, there are some significantly different viewpoints (alternative facts for those Trump supporters). But, these alternative facts are objective, actual facts.

Following this first TB revisited posting below regarding Practical Technology Solutions, I will be making additional postings as to Railroads: Individually vs. Industry, Suppliers: U.S. vs. International, The Customer Perspective, Pragmatic Scheduled Operations, The Regulators, Rail Operations; Domestic vs. International, Railroad Mathematics, Rail IT Architecture, PTC: What IT Is & What It Isn’t, and others that I may think of as time passes. I welcome your TB suggestions for my consideration.

PRACTICAL TECHNOLOGY SOLUTIONS
Being good at technology engineering does not necessarily make for being a good engineer when the bottom line is considered. There are several such examples in the rail industry that is still evolving from century-old technologies, e.g., track circuits, across much of the globe including the U.S. Arguably, the most telling and pathetic example is what the Interoperable Train Control (ITC) committee did in their development of an interoperable PTC system to address the Federal mandate of 2008. Below, I identify 4 primary issues in which ITC really failed each as to the lack of practical engineering in advancing PTC.

• The ITC designed an on-board positioning component to provide an accuracy of 18cm with 10-9 accuracy. Really! 7 inches with a risk of failure that will not occur in my lifetime? I assume this was based upon some vital track circuit / control specification developed over the ages. PTC is not vital in that it does not generate movement authorities and therefore does warrant such accuracy. In my rough estimation, this specification, if deployed, would raise the price of the component from $15,000 to $40,000 in my opinion – an unnecessary capital investment of $500 million plus ongoing maintenance for 20,000+ locomotives across the industry. I do understand that at least some of the Class Is have rejected such an over-engineered component, even though their collective technicians designed such.

• The monitoring of Intermittent Signals (ISs) were at least initially included in the specification. I don’t know where that stands now. However, with one estimate of 35,000 ISs across the industry at one point at perhaps at a price of $25,000 per installation, this would amount to another additional investment of $875 million plus ongoing maintenance with no added PTC or CTC value in that the Control Points are being monitored by PTC.

• A 220 MHz wireless data network is being installed without having performed any practical data modeling on what is really required for PTC, and without consideration of other technologies, including the 160 MHz network already in place. This was clearly a political move by NS and UP that had purchased the spectrum prior to and without knowledge of the PTC mandate. This amounts to a minimum $1 Billion unnecessary capital investment plus ongoing maintenance.

• Lastly, ITC did not involve the transits & commuter railroads in developing the interoperable operating rules. Hence, PTC as it stands could not prevent the recent in-terminal accidents where the passenger trains accelerated resulting in fatalities. Fortunately, this is a relatively simple fix via the use of GPS-fencing. The loss of life is already too much, and will only increase until PTC functionality is so expanded to consider the operating rules of transits & commuter railroads.

There are 4 primary technologies that should be addressed in a practical fashion as to their individual paradigm shifts within the last 2 decades that can advance both the safety and efficiency of railroads, as follows:

Communications
The U.S. railroads have been forced to install wireless data networks given the PTC mandate. Without that mandate, only a few railroads would have moved forward on their own with any urgency due to the lack of strategic wireless planning, both individually and collectively as an industry. Simply stated, knowing where the trains really are within a block (rather CTC or Dark Territory) AND the train’s speed is an absolute requirement for optimal “proactive traffic management” for medium to high density corridors, versus the crisis management that exists today given the lack of truly-scheduled operations. And, only wireless data networks can provide the necessary data for those traffic corridors. However, as noted above, the 220 MHz decision for PTC was poorly decided/forced for political purposes rather than functional / technical / economic reasons.

From a long term, strategic perspective, what are the railroads doing to take the most advantage of this wireless data infrastructure now that they have it, both individually and collectively as an industry? I expect little at this point.

Positioning
For the last century, track circuits have provided the necessary positioning information as to track occupancy/vacancy for train movement integrity for most of the railroad operations across the globe. Interestingly, 1/3 of the U.S. freight trackage, referred to as Dark Territory, does not use track circuits but rather communications between the train crew and dispatcher that uses a train sheet (now computerized- referred to as “conflict checker”) to manually determine occupancy / vacancy of track allocations. Now, with virtual positioning, e.g., enhanced GPS, those track circuits can be eliminated for the majority of railroads with the availability of wireless data and “vital” back-office traffic control software (which is akin to the conflict checkers used for Dark Territory) . It was with this practical engineering point in mind that my consultancy designed Virtual CTC (VCTC) for the railroads of both Egypt and Kazakhstan. There is at least one U.S. supplier that can deliver a VCTC-type system currently. But, don’t look to traditional CTC suppliers, in Europe especially, to provide such systems in that there would be a substantial loss in their revenues given the avoidance of wayside infrastructure required for CTC & ETCS-L2, as well as the on-going maintenance.

Traditional CTC engineers will argue that there will be the loss of broken rail detection / protection with the elimination of the track circuit. However, consider the following points. First, there are other technologies that can provide for such detection / protection, most notably the advancing fiber optics based systems as offered by at least Frauscher (www.frauscher.com). Second, many railroads across the globe do not consider broken rail detection / protection to be a necessary requirement for their railroad. Third, in the U.S., 1/3 of the freight trackage is Dark Territory and without track circuits. Hmmmmm!, FRA hypocrisy at work.

IT Processing
Since the 1970s, the IT processing platforms have advanced from mainframe to client/server to the cloud. But, what is still missing is that of the Mobile Node, i.e., the locomotive-borne IT platform. PTC has now established that for safety reasons, but with only limited expansion in to business applications, e.g., locomotive engineer performance. My development of the first overlay PTC was designed as a mobile node to address the shortcoming of BNSF’s ARES system back in the 80’s that provide limited PTC functionality via the back-office system. ARES’s design was highly susceptible to wireless data issues as to reliability and throughput. But then again, BNSF was constrained by on-board technology at that point. We are now past that with PTC, but where is the strategic perspective to take advantage of that mobile node as to customer service, dynamic work order, car monitoring, train diagnostics, track diagnostics, schedule performance, etc.?

IT Architecture
All railroads operating since the 70’s unquestionably have a Silo based IT Architecture (SITA), i.e., systems developed on an individual department by department basis without effective data interaction between the department’s systems. Certainly, SITA was justified with the introduction of the main frame computers at that point. However, SITA results in the duplication of data collection, storage, processing, and distribution of critical operating and administration data. This duplication results in both inefficient and unsafe operations. What is needed instead is an Enterprise IT Architecture (EITA) for the railroads, both individually and collectively as an industry.

My consultancy developed the first known design of a generic railroad EITA. This was done for Kazakhstan’s railroad, KTZ, that eliminates the tremendous duplication in the handling of data classes by disparate systems. EITA is Based upon a Single Source of Truth (SSOT) concept of designating singular data processes for generation of critical data. The classic approach to designing an EITA is referred to as Business System Planning (BSP) as first introduced by IBM in the late 60s (management consultancies have their own versions, but the basics are the same). The BSP process is very logical, but intensive, and it requires a firm commitment by upper management to participate because it takes on the individual departments’ IT fiefdoms. For further insight on EITA, I suggest my August 21, 2016 posting “The Market for EITA” on this blog in the “Railroad Business” category of postings on the right side of the Homepage.

For the U.S. freight railroads, it is critical that the EITA be extended to an industry level given the substantial amount of interchange between railroads. Simply stated, individual Class Is cannot run to schedule if the connecting railroads are not operating to schedule. To do so requires an efficient and timely exchange of operating status. That interchange of data does not effectively exist today due to both technical reasons as well the lack of truly scheduled operations by the individual Class Is.

So! Considering the ITC situations noted above, should the railroads continue to rely on their engineers for technology advancement given the lack of a bottom line perspective? Clearly, the answer is NO!  Also, the solution is not to look to many of the traditional suppliers because advance solutions can lead to reduced revenue due to lower capital investment and reduced on-going maintenance.

The answer to truly advance the safety and efficiency of railroad operations is to employ Strategic Technologists that can blend economics (business cases) with technology advancements to address specific advanced operations in a practical fashion. Such individuals are not employed now by railroads to my knowledge. Interestingly, the Class Is hired hordes of MBAs with the passing of the Staggers Act in 1980 to deal with the deregulation of freight railroad marketing. But now, it is well passed the time to bring in MBAs to address the practical tactical and strategic deployment of advancing technologies. For further insight, I suggest reading the article “Six IT decisions Your IT People Shouldn’t Make”, Harvard Business Review, November 2002, and substitute “Wireless” for “IT”.

In closing, I offer a suite of courses regarding Railroad Immersion (rational railroading basics), PTC, Advanced Traffic Control & Management, and Enterprise IT Architecture that address the spectrum of points noted above. These courses have been used by railroads and suppliers alike, both in the U.S. and internationally. A PDF brochure is available upon request. I am best reached at comarch@aol.com for comments and questions.

Vital PTC, Really?

I have been fortunate during my corporate management and consulting careers to take on and succeed with a wide assortment of assignments for which there was little to no precedence including the following:
• Architect of the first overlay Positive Train Control (PTC) system;
• Development of mathematical, financial, & liquidation analyses for the resolution of the bankruptcy of the Penn Central Railroad; the largest bankruptcy until that time;
• Development of a mathematical model for the blending of ferrous scrap to minimize the cost of electric furnace steel production;
• Development of an econometric model for the U.S. ferrous scrap market;
• Development of a computerized train crew management system;
• Design of a virtual Centralized Traffic Control (VCTC) system design for Kazakhstan’s and Egypt’s railroads; a system applicable to a wide variety of global passenger / freight rail operations including token-based, dark (non-signaled), and CTC railroads;
• Development of a wireless strategy for the U.S. rail industry based upon supply and demand;
• Development of a strategic Enterprise IT Architecture (EITA) for the U.S. intermodal industry;
• Development of an EITA for a generic railroad.

While the above list of engagements is diverse, the same primary, fundamental development concept contributed to their successful completion. That is, the more complex the challenge was, the easier it was for me to complete the assignment. That is, I have consistently taken a pragmatic, 80/20 approach to avoid the unnecessary, overly complex design issues that contribute very little value (20%), but that prevent others with their 100% perspective of being successful. The success of the 80/20 approach is directly dependent upon the ability to make the proper assumptions to avoid over-thought garbage – and then to revisit those assumptions once the air has cleared. There are two complimentary points that permitted me to be successful. First, I was in charge and could drive the solution to completion with little interference. Second, I was fortunate to identify and include excellent associates that were willing to support my efforts; it was usually a team effort. But, what happens when there is not an objective team and/or no rational (80/20) individual who is in charge? For example, consider the Federal Railroad Administration (FRA) and the Interoperable Train Control (ITC) committee relative to PTC and the concept of vitality.

To start with, it is necessary to define vitality in that there is a significant amount of misunderstanding across the industry, including management, regulators, and suppliers. So! Vitality is the process that is used to ensure the integrity of train movement authorities, i.e., only one train within a specified track segment at any time. In CTC operations, the vitality is within the wayside infrastructure of track circuits and control points. In Dark territory, vitality is the train sheet whether physical or computerized (conflict checker software). For some ex-colonies of the British empire, e.g., Egypt, vitality is the approach that provides for a physical token to be delivered to the driver, it can be that simple. However, to be clear vitality does not include the delivery of movement authorities, e.g., signals, cab signals, voice/digital transmission, or tokens.

Starting with the FRA’s Rail Safety Advisory Committee (RSAC) that took on PTC over a decade ago, there was the ongoing challenge on my part to obtain a common understanding that PTC is NOT “Vital” since it is not involved in the generation of authorities. The reason to make the distinction was driven primarily by my concern that undue risk analysis and system design would be sought by the FRA, if not suppliers and railroads, for PTC’s safety enhancement functionality that had no effect on the “vitality” of the railroad’s operations. My approach was to describe “functional vitality” in addition to “equipment vitality” that is associated with CTC wayside infrastructure. The functional definition was required to address how movement authorities are generated in non-signaled, “Dark”, operations since conventional suppliers have little to no experience with Dark. Hence, they will state that there is nothing “vital” there in that they only deal with equipment vitality. This “equipment” perspective made it too convenient for the FRA to fatuously associate the concept of vitality with PTC equipment while ignoring the concept of functional vitality for Dark operations.

FRA was not alone in abusing the vitality perspective. Specifically, the Interoperable Train Control (ITC) committee was also guilty of pursuing a non-pragmatic perspective of PTC presumably based upon what they thought was necessary for a seemingly vital system. This group of conventional Class I engineering and operational individuals, that were charged with designing an interoperable PTC perspective for the U.S. rail industry, far exceeded the necessary requirements for a non-vital PTC. I offer the following: 1) development a positioning accuracy for PTC that was totally ridiculous, i.e., 18 cm with 10-9 confidence level, 2) integrated the need to enforce to Intermittent Signals (ISs); and 3) forced the implementation of a parallel wireless data infrastructure without developing a data model for PTC and thereby not identifying alternatives that should have been considered. These were serious engineering design errors that resulted in a tremendous increase in the capital investment, on-going maintenance costs, and implementation time to install PTC across the industry. Additionally, ITC failed to take on the requirements for transits and commuter operations. An example of this ITC’s purposeful exclusion (ignorance, arrogance?) is the inability of the current PTC design to prevent the recent accidents due to trains over-speeding in passenger terminals. To be clear, such prevention requires no additional investment to that of PTC along the mainline. The solution requires only the addition of GEO-fencing for trains entering terminals. But, ITC’s lack of integration of the transits and commuter railroads in their activities means that such situations will not be included, at least in the initial rollout of PTC.

Now, FRA has made a declaration of “Vital PTC”. Some of the material I read on the FRA Website that discussed vital systems also had PTC enforcement functionality and were branded as Vital PTC systems – which they clearly are not. Rather, they are Vital Systems (traffic control) with integrated PTC-type functionality. How desperate is the FRA to make such inappropriate associations?

Along this same line of thinking, perhaps FRA is presenting the Vital PTC perspective in that the on-board PTC platform can also display digital authorities via the wireless data platform that PTC requires for its functionality. Hence, FRA considers this to be Vital PTC. However, there is a primary fallacy here. That is, the transmission of authorities, whether verbally, visual (signals), or electronically is NOT a vital function. Such transmission and display is safety critical at best, i.e., one wants such transmission and display to be highly reliable, but if it fails then the engineer resorts to the underlying vitality of any railroad. i.e. the Book of Rules.

I am encouraged by recent conversations with colleagues that the railroads are now pushing back on FRA’s declaration of “Vital PTC”. Welcome to FRA’s La La Land.

Rail-izing Positioning

Having lived in New Orleans (NOLA) for nearly a decade, I adopted the “positioning” methodology used by locals for locating a bar/restaurant/whatever in that crescent shape street infrastructure that romances the curve of the Mississippi. With such a fan-shape set of cross streets, one could not really use the North / South & East/West terminology that makes sense in cities with a rectangular street infrastructure. Rather, the folks in NOLA refer to a bar/restaurant/whatever as being Uptown or Downtown & Lake side (Pontchartrain) or River side (Mississippi) of the particular street. And, for many it seems, this is easier to remember and explain when jumping into a cab during a night of New Orleans’ revelry.

 

In the railroads, the positioning technology for tracking trains for a century or so has been to define the “block” of the track infrastructure occupied by the train without any accuracy of where in the block the train resides or at what speed it is traveling. And, unlike the case for NOLA folks, this positioning methodology doesn’t make sense anymore as railroads look for more capacity out of their current infrastructure. The railroad’s block perspective is due to the use of track circuits in conventional signaling operations for determining block occupancy. And even worse, roughly 1/3 of U.S. freight trackage does not even have track circuits for positioning – what is referred to as “Dark Territory” where the trains only “appear” to the dispatcher in spatial chunks of 20-40 miles when the train engineers  seek additional movement authorities.

 

Now, thanks to the U.S. Federal mandate of PTC, the railroads are required to implement a wireless data infrastructure. In my opinion this is the primary value of the mandate since PTC is far from being cost justifiable on safety benefits. Rather, PTC is a Godsend for railroads, whether they recognize it or not, because the mandate has forced the majority of railroads in the U.S. to make the transition to the digital age of wireless data that most Class I’s had been resisting due to the lack of a strategic technology plan aligned with a strategic operating plan, i.e., strategic railroading. But, what has yet to be railized by freight railroads is that the “virtual age” is upon them. Specifically, the use of virtual positioning technologies supported by the availability of wireless data can greatly reduce both capital and maintenance cost of railroad operations while significantly increasing the capacity.

 

The PTC mandate has forced the railroads to develop an accurate on-board platform that exceeds that of GPS alone.  The BAD news is that this component has been designed by technicians instead of technologists (who provide a bottom line perspective of the use of technologies) to far exceed the requirements for PTC. BUT, the good news is that this component provides the basis to make the transition from CTC to Virtual CTC (VCTC), both along the main line and in interlockings.

 

As presented in my previous posting on this blog, Railroads and the Virtual Age, VCTC means replacing physical block occupancy technologies, e.g., track circuits & axle counters, with virtual technologies that include an expansion of GPS with additional positioning technologies, e.g., tachometer, accelerometers, gyroscopes, GLONAS, etc., that are integrated via a Kalman filter (check Wikipedia) to achieve amazing, reliable accuracy even when GPS is not available in a tunnel, for example.

 

While a natural for mainline, VCTC’s capability with the addition of moderately accurate End-of-Train (EOT) positioning means that interlockings can use virtual technologies as well. After all, what is the real difference between mainline and interlockings? Answer: there really is not any difference that the proper use of technologies can’t resolve if technologists are involved.

 

BOTTOM LINE: The pursuit of VCTC, both along the mainline and in interlockings, offers freight railroads the opportunity to dump CTC. This is a fantastic opportunity for railroads as to both costs and efficiency if they can get their heads out of conventional operations. However, this is not good news for traditional CTC suppliers that benefit from the revenue of capital-intensive CTC infrastructure and the on-going extensive maintenance.

 

Welcome to the virtual age, you all. Even the NOLA folks have adjusted to virtual positioning (e.g., Google Maps), as we all have. But, they continue to use the uptown/downtown & lake side/river side description that is part of the charm of New Orleans. However, railroads don’t operate on charm. They operate on the bottom line, and VCTC along the mainline and in the interlockings is the future.

Shaken! Not Stirred

About 20 years ago there was a cartoon in The New Yorker, a monthly periodical best known, arguably, by non- New York City residents for its cartoons.  This cartoon showed two wealthy gentlemen (in the style of the Monopoly game millionaire) lounging in the bar car of a passenger train with their martinis. (I think of them as Reginald and Wilfred).  Reginald states:  “This is a lousy martini. (pause) This is a Hell of a way to run a railroad”.

Being a martini enthusiast (only gin of course),  I can appreciate the nuance of making such an evaluation.

Back then, this now-shallow perspective was in actuality one credible way to evaluate passenger and freight rail operations in that it was “take or leave it” from the railroads’ perspective of running their railroads. That is, railroads provided the service that they wanted to provide given their monopolistic position as to transport.  However, beginning with the availability of the interstate roads during the Eisenhower administration, followed by the passing of the Staggers Act in 1980 that deregulated the freight railroads as to the price that they could charge for services, there was a gradual, but sustained shift to the customer’s perspective. That is, with these two major game changes of the interstate road infrastructure and the Staggers Act, entered competition not only between rail and truck transport, but also competition between railroads.

In the last several decades, both passenger but primarily freight railroads have taken on a different perspective; a perspective on what technologies can deliver to make a railroad’s operation both more safe and efficient. I must state first of all, that US railroads, both passenger and freight, are extraordinarily safe, especially when compared to operations across the globe. (See previous posting “ What Price Safety” for some additional insight on this point.  But, I need to go back to the martini point.)

There are martinis, and there are martinis. James Bond’s infamous standard of “Shaken, not stirred” makes the point. But first, I should note that based upon an independent analysis of literature regarding James Bond’s life style, it has been determined that he was quite a drinker with his consumption of an average of 45 martinis within a given week. OK, so that is 6 +martinis a night which makes him somewhat suspect as to his objective credibility as quoted by Dorothy Parker of Algonquin Round Table fame:  “ I like to have a martini, Two at the very most, After Three I’m under the table, after four I’m under the host.” So!  6+ martinis in an evening is clearly past the line.

The point of shaken, not stirred, can be applied to railroad operations, me thinks.  The difference between the two versions of martini preparations is that if a martin is shaken, then the ice can “bruise” the gin, where as stirred is like “Whatever, don’t mess with my gin.” Therefore, the parallel to railroads, you may ask, is that railroads have only been stirring their operational processes for the last several decades, at least, by simply upgrading their primary core technologies, i.e. communications, positioning, and IT, most noticeably with the shift from analog to digital, and the integration of distributed decision making platforms with the back-office infrastructure. But, railroads have not truly shaken up their business processes, a.k.a. process reengineering (dynamic work order is a good example), to take advantage of how the operation can change with advancements in technologies. Arguably, the most critical example is that of the management of train movements as to the underlying means of functional vitality (how movement authorities are generated) and the efficiency that an be achieved with more timely and accurate positioning of trains to advance from crisis-based fixed block operation to that of proactive, flexible block.

In this light, the passing of the Rail Safety Improvement Act of 2008 that mandates PTC deployment across most of the freight and transit rail operations in the U.S. has been both a blessing and a curse. That is, the PTC mandate is forcing the railroads to deploy an industry-based wireless data platform with mobile IT platforms on locomotives. That’s super. But, the over-engineering of PTC and the lack of technology strategy across the industry, has dampened the progressive advancement of business processes that can use these technologies.  Simply state, there is no business strategy in sync with a technology strategy, a.k.a. Strategic Railroading, in most of the railroads, yet alone with an industry perspective for freight operations.

So! Do you want to shake things up in your railroad – or your client railroads if you are a supplier? Or do you just want to stir the same old stuff, the same old processes, albeit with upgraded technologies? If you want to shake things up, then consider what can be done with virtual positioning and wireless data technologies.  For one example, click on the VCTC category on the right side on the home page of this blog and review the postings.

Finally, permit me to add my personal notes on gin. With my 46 years of legally enjoying gin across the globe, I offer my following evaluation of several:

  • Bombay Sapphire: a classic, a standard, not insulting to anyone.
  • Hendricks: Just too much rose – only good for 1 a month
  • Blue Coat: made in the U.S and excellent, but then again keep it down to several week if you drink your martinis dry.
  • Gibson: my favorite when in France – can’t find it in the U.S.

In the spirit of full disclosure, I should note that I wrote this posting while drinking wine only. Wine is for thinking and writing … and Martinis are for neither.

What Price Safety ?

On December 1, 2013, there was an accident on the Metro North Railroad (MNR) that resulted in 4 fatalities. In some 30 years of operation, this was the first accident on the railroad that resulted in passenger fatalities: quite a phenomenal record for any form of passenger transport. The source of the accident was the failure of the driver to reduce the speed of his train on a curve with the train flying off the track. The reason for his failure was, according to the driver, his dozing off.

There are actually two systems available on MNR to prevent accidents due to such driver errors with a third system due before 2016. However, neither of the current systems could be used by that given train on that given portion of track.  First, there is an alertness system that requires the driver to perform some action (e.g., touch a button) with a certain frequency (e.g., every 25 seconds) to silence an alarm and prevent an automatic brake application.  However, for this train that system was available in the locomotive in the front of the train, whereas the driver was operating from a position in the rear of the train. Second, unlike freight railroads that use wayside signaling, MNR (and many transits) uses cab signaling which in addition to knowing block occupancy and track divergence can include civil speed enforcement if such data is provided to the on-board platform. For that portion of track, there was no such data provided –that would have permitted the cab-signaling platform to enforce.  But, there is now.   Now, with the mandate to implement Positive Train Control (PTC), there will be a third enforcement approach that will prevent accidents due to driver errors including overspeeding anywhere along the track, passing the physical boundary of the movement authority, moving through misaligned switches, and entering a work zone without permission.

So! What price safety? Without any hard figures to back me up, my experience tells me the following:

  1. Alerterness systems are relatively inexpensive, but also somewhat limited as to safety value;
  2. Cab signaling is a no-brainer for transits. It is both a traffic control (versus very costly wayside signaling) and an enforcement system, although somewhat limited when compared to PTC.
  3. PTC is extremely expensive, but the most comprehensive in preventing accidents. However, as has been demonstrated by independent parties, the Cost / Value ratio of PTC across the rail industry is quoted at 20 to 1 for a 20 year period. However, my personal view is that the ratio is more likely 10 to 1 if the freight railroads’ technicians had not done such an irresponsible technical and functional overdesign of PTC (postings on this point are available by clicking on the PTC category on the right side of the home page.)

So! Perhaps a better questions is: Who should pay for a mandated system whose cost far exceeds its value?  In the case of the transits with both alertness systems and cab signaling there is another question that has not been answered to my knowledge: What is the true Cost / Value ratio for transits given that PTC provides incremental increase in safety given the use of alerterness systems and cab signaling?  This analysis would result in a higher Cost / Value ratio. And, does a government-owned entity really want to spend that kind of money for that incremental safety benefit?

Now, to the ridiculous of What price safety?  On the day following the MNR accident, I was contacted by CNN to see if I would be willing to be interviewed by Brooke Baldwin during her 2-4 PM show. They had interviewed me previously regarding the horrific train accident in Spain in July, also due to operator error as to overspeeding on a curved section of track. (As a side note, my colleague Dave Schanoes handled the evening show on CNN for both the Spain and MNR accident.) I was asked if I could discuss the use of seat belts on trains as well as federal regulation regarding train safety. After a silent gasp of “REALLY, you’re serious?”, I thought I was clear with them that I need not address the issue of seat belts, but surely no problem with the regulatory issues.  So! Guess how the 3 minute interview went.  The first question asked by Ms. Baldwin:  ” Ron, let’s just cut to it. Is it about time that we have seat belts on trains?”  With a smile I replied “That’s a very interesting point.” and went on to get the conversation back to a rational understanding that we run a safe railroad … and so on….  and that PTC is not justified.  Closing with “What cost safety?”  click here to see interview: cnn interview

Just as the mandate of PTC was a knee-jerk reaction by Congress to the Metrolink / UP accident in September, 2008, I have little doubt that there is some local, state, and/or Federal politician that would like to run with the seat belt concept.

 

THINK

When I joined IBM in 1970 as a Marketing Representative to sell computers, I was presented with a 10 inch plaque for my desk that simply stated “THINK”.  I still have that plaque on my desk.  Since that time of the commercial introduction of computers, corporate America has been proceeding through 3 stages of THINK as to their business environment. As addressed below, the U.S. freight rail industry has kept pace with the first two stages of Digital and Process Reengineering to a respectable extent, but the railroads have yet to fully embrace the 3rd stage, Connectivity, which is extremely critical for railroads to manage their primary reliance on mobile resources, both individually and collectively as an industry.

1: Digital

With the marketing of computers in the 70s, IBM realized that its first primary challenge was to educate its clients’ executives as to the opportunity to use computers to replace the straightforward processes that were handled by clerks, e.g., payroll, inventory update, accounts receivables / payables, etc.  These sequential processes of updating data bases were readily handled by the predominance of magnetic tape-based, sequential record data bases. THINK back then was how to make the business case for top-level management to lease these intimidating physical electronic monsters (purchase was not an option at that time with IBM).

 

To take on this challenge of converting manual (analog) processes to digital ones, IBM was hiring two basic types of disciplines, i.e., MBA’s and teachers. The former (which I was) were used to provide the business case, e.g., the discounted present value of advancing a business process, and the latter were used to present the business case.  With the phenomenal amount of Sales School training that IBM provided to its marketing personnel at that time, these two disciplines were blended to provide an unprecedented marketing force. We didn’t have PowerPoint, of course, but we were well trained on paper “flip chart” presentations that permitted us to efficiently make our “bullet” presentations to client executives.

 

As a side point, IBM’s Marketing Representatives were also trained on basic marketing/sales concepts such as

  • Shut up once you asked a question of the client so as to permit that individual to reach his / her own conclusion based upon what you had presented;
  • Once the executive agreed to the sale, you introduced no additional thoughts;
  • It takes 10 cold calls to close 1 deal;
  • Do not disparage a competitor directly. However, one could state demonstrated truisms, e.g., “Burrough’s computers perform 1/3 slower on your accounts receivables as demonstrated by the benchmark test that we performed with your data.” If you violated this principle, then it was very likely that you were soon on the street.
  • One never had alcohol at lunch  – unless the customer insisted, at which point you didn’t go back to your office or to that of your clients;  and
  • One dressed based upon the dress code of the customer – as long as it was a dark suit and a white shirt.

While IBM set the high water mark for ethical behavior in the Data Processing industry (the phrase for Information Technology back then), if not elsewhere, there was no question as to the benefit of such behavior including a most important advantage that an IBM business card would get you pass the secretary of almost any executive. Those were the good ole days, in that marketing was above board. Again, an IBMer would be fired immediately if s/he violated IBM’s sense of business ethics; ethics that were and are still unmatched in the US business (and political) environment in my opinion.

At this point in time, THINK was more about hardware than it was about software. Within a decade or so, the perspective of THINK advanced to Stage 2 with the transition from sequential tape processing to that of dynamic, direct access to data via affordable disk drives and the associated advancement in software.

2: Process Reengineering

For the last several decades, the concept of THINK has been all about functional understanding of what a business process is attempting to achieve. Some readers may recall the rush to Process Reengineering in the 90s. Simply explained, process reengineering meant reTHINKing how processes were handled as to workflows given the use of computer processing and wired telecommunications that integrated otherwise disparate entities in a company. This was a holistic perspective of the company and, in selected cases, an industry. However, the ability to reengineer processes was most often directly related to the ability to use wired communications between the sub-entities for the purpose of distributed, but integrated processing. However, for industries that are primarily about managing mobile resources, e.g., railroads, process reengineering was greatly limited in that a wired path can’t be attached to a locomotive. As a side point, IBM had developed an extraordinary concept of Business System Processing (BSP), a.k.a. Information System Processing (ISP) that proceeded process reengineering by 2 decades to optimize data storage. I have a posting on BSP that can be found by clicking on the category of Strategic Railroad on the right side of the home page and paging down to It Takes an Industry: Process, April 14, 2012.

3: Connectivity

With the ubiquitous availability of wireless data networks now, whether commercial or private, the 3rd state of THINK now also includes who “THEY” are that are involved in the functionality. This is an issue of connectivity, with a minor in functionality. For railroads this means tightly integrating the management of its trains, crews, locomotives, and maintenance with the back office systems based upon a very simple principle: “Where are my trains (I mean really where are trains other than just a block), AND at what speed are they traveling. This is all about running a truly-scheduled operation. The ultimate, but largely unachievable, example of this is moving block. But, short of that is the role of Proactive Traffic Management (PTM) that minimizes the consequences of traffic conflicts in dense corridors, and that can support “flexible block” operations versus the inefficiency of fixed block operations with traditional CTC operations. I have a posting on PTM that can be found by clicking on the category Strategic Railroading on the right side of the home page, and paging down to Degrees of Separation, December 26, 2012.

 

With the mandate of PTC, the freight rail industry has been forced to develop an industry-wide wireless network, which is clearly the true value of the PTC mandate given that our freight railroads are already extraordinarily safe. For those individuals that are still confused about the business benefits of PTC, please, please understand that PTC does not deliver business benefits. It is the availability of a wireless data network required for PTC implementation that can provide those benefits – as evidence by NS and BNSF, at least, that are achieving those fatuously proclaimed PTC benefits by some misguided individuals without the implementation of PTC.

An article of mine is scheduled to be published in the forthcoming C&S issue of Railway Age, and it will describe the pursuit of this stage, not just from an individual railroad standpoint, but also as what can be done to increase the efficiency of the U.S. freight rail industry. The underlying principle here is that a railroad is limited to its ability to run to schedule if the railroads with which it interconnects are not running to schedule, and visa versa.  In my opinion this Catch 22 can best be resolved by 2 means. First, railroads require PTM (with a glazing of flexible block), and Second, the annual bonuses of railroad executive must include a performance measurement as to Industry Efficiency. However, it is unlikely that the pursuit of industry efficiency will happen until there is a true Strategic Industry Railroading perspective that involves all of the Class Is.  So! Who will provide that industry strategy?  Hmmmmmm! It appears that there is a role for an independent consultant. Please call: (904) 386 3082.

Innocence Lost: Rail Operations

In the previous posting on this blog, I wrote about the Innocent Lost of Engineers, meaning that with the introduction of the commercially-available, hand-held digital calculators in 1972, engineers began to lose their ability to approximate solutions for a series of calculations with various powers of ten involved.  For example: engineers of that generation could quickly determine that 3.936 X 44,888 / 1,987 is somewhere in the range of 4x(90×500)/(4×500) …hence … 4×90/4 … hence …  90. Such capability was an art that complemented the use of the now-obsolete slide rule, an analog calculation device that performed multiplication and division by literally sliding sticks ruled with logarithmic scales. This lack in the skill of approximation for engineers not experienced with the slide rule is unfortunate because it is critical for thinking on one’s feet to obtain answers to move through complex situations efficiently, albeit not accurately. I also believe the ability to approximate solutions adds greatly to one’s level of creativity. Unfortunately, engineers of today feel compelled to deliver exactness limited by the number of digits displayed on their digital device. Their answer for the above problem would be 88.91754806240564…

Considering railroads, I see a significant lack of creativity with the current set of primary technicians across the industry as to their inability to “think outside of the boxcar, if you will. A case in point here is the pursuit of PTC in the U.S. where technicians are designing to extreme levels of exactness and capability that are clearly not warranted (see posting The Goods, The Bads, & The Uglies, March 5, 2013  found by clicking on the PTC category on the right side of the home page).

Now, I suggest that railroad operators are in the process of losing their innocence as well as to how they run their railroads. Fortunately, however, this is a good thing. Instead of operating a railroad as they have in the past to satisfy their own perspective of what a railroad is, i.e., take it or leave it, railroads are focusing now on customer service for the benefits of their own bottom line as well as that of the shippers by improving customer service. This customer / bottom line perspective started to evolve in the 80s as railroad executives began to recognize the increasing amount of freight traffic being captured by the trucking industry via the nationwide interstate road infrastructure. As a subject for a posting in the future, this was the genesis of the intermodal industry that has now replaced coal freight revenue as the top source of revenue for several Class I railroads.

As to operators losing their innocence, I see 4 phases that will permit them to eventually maximize the use of their resources while delivering optimal customer service.

  1. Resource Rationalization
  2. Scheduled Operations
  3. Proactive Resource Management
  4. Industry Management Perspective

Unfortunately, as explained below, most of the major U.S. railroads have only managed to achieve the first phase of resource rationalization in the last 2-3 decades. Too few railroads have begun to pursue the 2nd phase of scheduled operations, yet alone the 3rd phase of proactive resource management, and certainly not the 4th phase of industry management perspective.

1.    Resource Rationalization

This phase began with the signing of the Staggers Act in 1980 that deregulated the freight rail industry in the U.S. This act introduced competition to the freight rail industry by removing the role of the now-defunct Interstate Commerce Commission (ICC) that regulated the tariffs for freight services. This first phase was managed via the infusion of MBAs in the railroads that struggled to work within the efficiency constraints of conventional traffic control systems and the associated operating processes. Such constraints included being confronted with the mindset of operators that fatuously believed that running a railroad without a true schedule was a test of their management skills. That is, a train schedule was something that was handed down to them by the ivory tower Service Design department staffed by MBAs, as “wouldn’t this be a great way to run a railroad”. But, a true operator was not being measured by such performance, but rather by his ability to work with conflicts as they occurred in traffic movements. Hence, what the MBAs provided at that point was limited to an analysis of contribution of individual rail corridors as to the railroad’s bottom, although that analysis was based upon non-scheduled operations. The result of their efforts was the shedding of rail corridors with less than acceptable performance. Unfortunately, the other primary assets, e.g., locomotives, rolling stock, crews, yard operations remained untouched as to their inefficiencies.

2.    Scheduled Operations

The railroads are now into the second phase of losing their innocence with the advancements in technologies, most importantly wireless data an virtual positioning, that can provide for more timely and aggressive handling of train movements by simply knowing where the trains are AND at what speed they trains are traveling. For most railroads in the U.S., they have only begun the process of deploying the necessary wireless data networks that can provide such data. It should be understood that this wireless deployment is not due to a strategy on the part of most railroads, but rather it is a deployment due to the Federal mandate to implement PTC, a system that requires a wireless data network.  I dare say that without that mandate, a number of railroads would still not being deploying such data networks due to a lack of operating strategy linked with a technology strategy (a.k.a. strategic railroading). For example, to my knowledge only 2 railroads in the US had such a strategy before the mandate to deliver the data required to improve the efficiency of their crisis-based dispatching processes.

 

With this additional level of timely and accurate train position and speed data, the challenge of efficiently dispatching trains increases beyond the mental capability of any dispatcher to deal with all of the variables in dense corridors. One should understand that effective dispatching until this time had been an art based upon not only the mental capabilities of the dispatcher, but also by his/her degree of experience with a particular corridor. And, based upon the principle that one can not effectively manage dispatching if one cannot measure the efficiency of dispatching, then I suggest that no major railroad had, and perhaps has, any effective measurement technique as to the efficiency of its dispatchers. Maybe, they think they do, but most likely it is based upon the conventional concept that a dispatcher should not make the same mistakes that s/he made yesterday, or the day before, or the week before, whatever.

Operating to schedule is not just about track time efficiency. Class Is are beginning to realize that the ability to run to schedule can result not only in better customer service, but also in a substantial reduction in the “slack resources” (a mathematical phrase when optimizing operations) that sit idle so as to permit some level of efficiency when locomotives are not where they need to be … or train crews outlaw … or the designated yard has insufficient in-bound tracks, etc. Simply stated, the unstructured inefficiency of depending upon the use of slack resources in a crisis-based, truly non-scheduled fashion is substantially greater than running to a schedule where slack resources are kept to a minimum to handle a substantially less level of conflicts when the schedule is corrupted…which is more the case than not.

3.    Proactive Resource Management

This next phase is that which only 2 Class Is to my knowledge have taken on. I introduced PTM a decade ago based upon a very simple construct. That is, in order to minimize conflicts of mobile assets, then wireless data is required to provide the timely and accurate data of where those assets are AND at what speed they are traveling.  With such information, then mathematical planners (basic algebra) can be used to predict where conflicts will occur. With that knowledge, then Operations Resource (OR) tools can be used that identify objective functions to minimize the consequences of those conflicts. For example, an objective function may be to reduce the travel time, or to maximize train velocity, for the set of trains being considered for a particular corridor, or for a set of corridors. Conventional CTC that is used across 50% of the U.S. freight rail trackage can only provide block occupancy with no knowledge of speed. For example, did that intermodal train come to a stop, and therefore the opposing merchandise is train being held on a siding for no reason? The other 50% of the freight trackage is dark territory where the dispatcher doesn’t even know which the block the train is in, yet alone the speed. Simply stated, PTM provides for flexible block operation (which is far short of the complexity, if not the questionable possibility of moving block) instead of the inefficiency of fixed block operation where trains vary significantly in length and speed. For further information on PTM, I suggest you read the posting Degrees of Separation, December 26, 2012 in the category Railroad Business found on the right side of homepage.

 4.  Industry Management Perspective

There  is a 4th  phase, which has yet to be initiated, that addresses the efficiency of the industry, and not just an individual railroad. The underlying point here is quite straightforward, but yet continues to be ignored. That is, given the substantial necessity of trains across U.S. railroads to operate within a specific region, yet alone to go from coast to coast, it is impossible to achieve the highest level of scheduled railroading if the interconnecting railroads are not running to schedule. So, there is a Catch 22 in that a given railroad cannot operate at its highest level of efficiency until the interconnecting railroads are running to schedule, but those railroads cannot operate to schedule until the given railroad is operating to schedule.

 

I see 2 requirements to break into this circular logic. First, the increasing use of PTM will narrow down the complexity of the interconnection challenges. Second, and most important, the annual bonuses of railroad executives need to be structured to place emphasis on industry efficiency, and not just the efficiency of their individual railroad.

 

Lastly, for the majority of railroads in the U.S., as well as for a number of low density corridors in the Class Is, there is still an issue of considering how wireless data, virtual positioning, and on-board intelligence (such as that being provided via the implementation of PTC), can replace their current dark territory and low density CTC operations with Virtual CTC (VCTC) as described in other postings, including videos, on this blog (click on the VCTC category on the right side of the homepage).

 

All of the above is really quite straightforward to understand, but the traditionalists of railroads have yet to grasp that a paradigm shift is available to them given a shift in the core technologies that is available to them: again, wireless data, virtual positioning, and on-board intelligence.

Innocence Lost: Engineers

Prior to the commercial introduction of the handheld digital calculator by Texas Instruments (the developer of the integrated circuit, a.k.a., micro-chip) in 1972, the act of performing mathematical calculations was often by means of the slide rule, a handheld analog calculator, that “miraculously” performs division / multiplication by adding / subtracting log scales via sliding bars. Using the slide rule back then was both a science and an art; an art that is now lost for those engineers nurtured only by digital technologies. That is, with the slide rule there was a certain level of innocence for those folks, myself included, in that we had to accept a marginal level of accuracy (versus doing time consuming, long hand mathematics) based upon the granularity of the scale provided on the sliding bars – what is referred to as significant digits. However, with the digital calculator, the accuracy level is only restricted by the number of digits displayed on the device.  For example, 8 / 3 on the slide rule would only permit a solution of 2.7 due to the principle of significant digits. However, on the digital calculator with 8 digit displays, for example, the answer would be 2.6666666. One consequence of such innocence, now also lost, was determining the placement of the decimal point in a series of calculations. For example, using the simple 8 / 3 calculation, the manipulation of the slide rule would be the same for 800,000 / 3 as it would be for 8 / 3.  Hence, the approximation of 2.7 shown on the slide rule required the user to interpret this as 270,000 – versus the 266,666 displayed on the digital calculator. And, for a series of calculations, this could indeed be a challenging effort.

 

The point of the above is that the innocence of approximating answers based upon significant digits and placing the decimal in one’s head has been irreversibly taken from us with the onslaught of the digital age. Unfortunately, this lost of innocence, in my opinion, has placed a fatuous belief in the importance of absolute accuracy, versus the pragmatic perspective of what really is required for a given situation. And, I suggest this difference is proving to be very expensive unnecessarily in the development and deployment of technologies across the majority of the rail industry that doesn’t deal with high speed / high density operations. Simply stated: Rail time IS NOT Real time for the majority of railroads across the globe.

 

A primary example of Rail vs. Real is the collection of PTC efforts in the U.S.  For the pragmatist, the timeliness and accuracy of train position and speed required for traffic control, traffic management, and enforcement (my generic term for PTC) for the majority of railroads across the globe, is rather basic and inexpensive to provide compared to the technical architecture being developed by the Interoperable Train Control (ITC) committees charged with designing PTC. To expand my point, I refer you to my previous posting on this blog as to the “The Simplicity of Complexity” where I refer to the “80/20” rule, i.e., where 80% of an objective of (choose a topic) can be achieved with 20% of the resources required to achieve 100% of the objective, if that 100% is even achievable. Applying the rule of 80/20 to PTC and traffic control /management (see my postings on VCTC), then unlike those individuals raised on digital precision, the position AND speed of trains in supporting PTC and effective traffic control / management is greater than that provided by fixed block signaling systems, but substantially less than real time. That means that engineers charged with designing virtual positioning approaches, e.g. GPS, and wireless data infrastructure to deliver the data for on-board enforcement as well as to the back office control / management systems, do not require anything approaching the complexity of the technologies being designed for PTC. Yet, our current breed of technicians that have been raised exclusively in the environment of digital communications, video games, and the instantaneous and unlimited throughput of wired IT architecture, do not have that 80/20 perspective. For example, why does a railroad need a level of positioning accuracy for PTC that far exceeds the accuracy of the braking curve for enforcement? And, yet, that is what has been designed by ITC. As to wireless, why do the railroads need a 220 Mhz network in parallel to the already installed 160 Mhz infrastructure? Actually, I know the answer to this wireless question, and it has to do with the failure of the railroad technicians (and their management) to develop a pragmatic strategy of what they could have done to replace their analog 160Mhz platform with a digital trunk system (e.g., TETRA) that would have greatly increased the capacity of that infrastructure to not only handle PTC, but also to readily handle the wireless voice requirements of crowded metropolitan areas such as Chicago and Kansas City.  Ok, so perhaps that last sentence is a bit technical here, but it shouldn’t have been for technicians that should have sought out pragmatic solutions.

 

The bottom line is that US railroads, for PTC implementation alone, will be investing $Billions more than that which is really necessary. One could perhaps make the argument that such an investment will have other benefits in the future such as developing an industry-based strategic operations plan involving the effective interchange of trains, chain of custody, asset and shipment management, etc.  BUT, that strategy does not exist … and nor will it until railroad executives are compensated via their personal objectives and associated bonus program to take such a viewpoint.

 

In a forthcoming posting I will be writing about the Innocence Lost: Rail Operations, But unlike the innocence lost for engineers, this will be a very positive perspective because it really addresses the Ignorance Lost.

The Simplicity of Complexity

During my 5 decades + of post-graduate experience in handling a wide variety of positions that have involved technical, functional, and mathematical challenges without any precedence, it seems that I have purposely sought out those unique engagements without any obvious solutions. I have done so based upon what I have proven to myself to be a truism: the more complex an engagement appears to be, the easier it is to resolve.   Although this concept is counterintuitive for most folks I expect, and not as true when dealing with leading-edge technologies, the fact is that too many professional types tend to over-think what needs to be done when it comes to threshold technologies. I am referring to those basic technologies that provide the data to support the processes that are required to manage one’s company’s operation in a truly cost-effective fashion. Unfortunately, it seems to me that the more that STEM (Science, Technology, Engineering, & Mathematics) individuals are engaged with the subject at hand, the greater the risk that the solution will be over-thought … and therefore over-engineered … and therefore unnecessarily over-expensive as to both investment and maintenance. What is missing by the STEM professionals, in my opinion, are two primary principles of an MBA.

 

First, is the understated (and therefore underappreciated) principle in the application of statistics and realizing the rule of 80/20. That is, the variance in the coefficients of variables (if not the ability to identify all variables) that are required to make a mathematical / functional / technical analysis of (choose at topic) means that 100% of the objective is never achieved. Rather, one shoots for 80% of (chosen topic) which will require only 20% of the cost to purse an acceptable, achievable goal of (chosen topic).

 

The second principle of the MBA is to provide a Bottom line, Business perspective to what is being sought. This perspective suggests that STEM should be modified to be STEM-B. Below, I discuss Both the simplicity of complexity, the 80/20, as well as the Bottom line perspective. The distinction I am making here is the difference between STEM Technicians and STEM- B Technologists.

 

Complexity / Simplicity

As an example of the simplicity of complexity, I reflect on the early days of the U.S. space program. At one point, there was a significant effort on the part of space STEMs to develop a solution for astronauts to shave in a gravity-free environment so as to prevent the shaved whiskers from fouling the on-board electronic equipment. Several solutions would have been to use only Native Americans or female astronauts (assuming that smooth legs would not be a requirement). After significant research in vacuum-capture systems, the chosen solution at that time was to use a razor in concert with shaving cream that would capture the severed hair particles – how effective, how pragmatic.

In this vein relative to railroads, PTC is a prime example of how the technicians have clearly blown it. As addressed in earlier postings on this blog, these folks have totally over-engineered not only the functionality of PTC, e.g., the enforcement of intermittent signals (ISs), but also over-designed 2 of the 3 core technologies of PTC, i.e., communications and positioning (see posting on March 5, 2013 titled “The Goods, the Bads, & The Uglies” that can be found on the blog by selecting the category of “Strategic Core Infrastructure” on the home page). At least the third core technology of Information Processing was well thought out as to the use of 2of 3 processors to ensure the availability of the on-board PTC platform to avoid regulatory requirements to proceed at restricted speed should the PTC unit fail in route.

So! What is the simplicity of complexity? By this I mean that if one takes an 80/20 perspective of what can be accomplished by making good assumptions, then solutions can be realistically achieved.  For example, no railroad is 100% safe, even though the FRA fatuously states that there should be ZERO tolerance for unsafe railroad operations. The truth is that a railroad’s operation has 0% chance of being 0% unsafe unless it runs zero trains. That doesn’t make any sense, of course, and such expectations of absolute safety results in overbearing regulations such as the PTC mandate (thanks to a knee jerk reaction by Congress to the horrific MetroLink – UP accident in 2008) that is clearly not cost-effective for U.S. railroads. When I designed the first overlay PTC system in the U.S., and subsequently in Egypt (as discussed in the most recent postings on this blog), I made a 80/20 evaluation of what could be achieved with the technologies at hand relative to the operating environment of most railroads across the globe.  For example, it was clear that a vital system (that which generates the movement authorities for trains to advance) that integrated traffic control with enforcement, such as moving block, was not technically nor functionally achievable in a cost-effective fashion due to technologies, operating practices (including the handling of yard operations), given that the majority of train movements are unscheduled both within and between railroads (interchange). In the case of Egypt, the issues are even more complex given the use of “vital employees” that manually generate movement authorities. Hence, I designed Virtual CTC solution (VCTC) to address what could be done cost-effectively to prevent the majority of accidents in the U.S. as well as both the safety and efficiency of the Egyptian National Railways (ENR) and the majority of small and medium railroads across the globe. This process required making assumptions as to what was really needed for safety – an analysis that subsequently proved to be right on. Do these solutions meet the FRA expectations for ZERO tolerance? – Absolutely not – BUT, then again, nothing can. However, VCTC is very cost-effective … and exactly what the Egyptian Railways and many other railroads across the globe need to make their railroads financially viable while providing unprecedented safety not achievable with conventional operating systems.

Being 80/20 in one’s thinking means having the mental and institutional ability to be creative, To be mentally creative means having the ability, again, to make assumptions that eliminate that 20% of the problem that can’t be achieved in any reasonable fashion, and then design a solution, followed by a subsequent review of the assumptions made to be sure that nothing critical was left out.  As to institutional freedom, I am referring to the organization permitting its employees to pursue justifiable, cost-effective solutions that make financial sense. Unfortunately, it would be naïve to ignore the fact that most executive bonus programs are based on the near term, without a long-term strategic perspective, that may restrict such a process.  A case in point here is the lack of an industry-business perspective by the US freight railroads that could deliver interchange data for minimizing the effect on scheduled operations. That is, a railroad dependent upon interchange is constrained to running to schedule if the other railroad is not running to schedule, and visa versa. This is an industry issue. (Does any railroad have the evaluation of interchange efficiency in its executive bonus program?) Interestingly, it is the PTC mandate that is forcing the railroads to develop an interoperable, industry-wide wireless data infrastructure that can deliver such industry wide applications for the benefit of all. Without that mandate, it is my opinion that the technical solutions of individual railroads would have prevented such a strategic perspective. This point introduces the second issue of addressing the bottom line.

 

The Bottom Line

So, how did the technicians manage to ignore the bottom line with the over-engineering of PTC to meet the PTC mandate?  And, arguably more important, why is there no Industry Strategy on how an industry-wide wireless network, that will be delivered to meet the interoperability requirement of PTC, can benefit the railroads both individually and collectively (e.g., the ability to improve scheduled performance with the availability of timely interchange data of foreign trains …  or … How is that foreign locomotive in the lead of the train on my property performing?)

On June 6, 2011 I made a posting “Six Wireless Decisions Your Wireless Management Shouldn’t Make”  (which can be found on this blog by selecting the category of Strategic Railroading on the right side of the home page, going to the bottom of the postings that are provided and then clicking on Older Entries). This posting paraphrased an article in the November 2012 issue of the Harvard Business Review (HBR) titled “The Six IT Decisions Your IT People Shouldn’t Make”. Simply stated, the HBR article makes the point, and my wireless version parrots, that operations management fails “to recognize that adopting systems poses a business – not just a technological- challenge. Consequently, they (a company’s senior management) don’t take responsibility for the organizational and business process changes the systems requires.” The result of this lack of involvement is that the CIO (or CWP – Chief Wireless Person), with a technology perspective exclusively, is constraining the advancement of the company’s business processes, and most likely the return on IT (or wireless) investment and, more importantly, the company’s bottom line.

In that prior posting I suggested the following 6 decisions that the CWP shouldn’t make as to wireless in sync with HBR’s article as to CIOs and IT.

  1. How much should we spend on wireless?
  2. Which business processes should receive our wireless dollars?
  3. Which wireless capabilities need to be company-wide (and industry-wide)?
  4. How good do our wireless services really need to be?
  5. What security and privacy risks will we accept?
  6. Whom do we blame if a wireless initiative fails?

To add my personal touch here, I list below some questions that the senior railroad executives may want to ask their Engineering and Operations management.

  1. What are the plans to use the wireless data for our internal purposes?
  2. What is the strategy for the industry to use the forthcoming wireless data network?
  3. What accuracy do we really need for train positioning and speed?
  4. Does CAD provide the necessary traffic management tools to perform proactive traffic management?
  5. What can be done to improve the reliability of interchange to increase scheduled operations?
  6. Does Operations know the condition of the foreign locomotive in our trains?
  7. How do we measure the efficiency of the dispatchers?
  8. Is Service Design aligned with what can be done with timely train position and speed data as to developing an achievable train schedule?
  9. Why oh why are railroads enforcing ISs for PTC?

The closing point is that the rail industry needs technologists, in sync with technicians, that can deliver solutions based on the bottom line, both for individual railroads as for the industry.  The railroads are not on schedule here as well.

Follow StratRail on Twitter
Strategic Railroading™
Given recent tech advances there is now an unprecedented opportunity to advance railroad operations and the integration of high speed rail with freight. Real-time traffic management and communication is possible without significant development and deployment costs, but it will take a technology strategy working hand-in-hand with an operational strategy, it will take Strategic Railroading.™
Full Spectrum - Quarterly Journal

Full Spectrum is a quarterly railroading journal authored by Mr. Ron Lindsey. The majority of executives in the US railroad industry, including top members of the FRA and the major railroads, have subscribed to Full Spectrum for the past fifteen years.

Full Spectrum subscriptions are available by contacting Ron via email. If you are concerned with staying abreast of the newest advances in rail technology or operations strategy, it is highly recommended you subscribe in order to maintain your competitive advantage.

Back issues are on sale here.

Purchase Full Spectrum Issues
Your cart is empty
Visit The Shop